2010 Water & Wastewater Construction Projects

Environmental Services
 
Roads Construction Projects
  WATER & WASTEWATER

Georgina WTP - Phase 2 Expansion
Project No. 72500
Contract No. T-09-80
Project Description:  This work includes the phased construction of a new water treatment plant to service the Keswick and Sutton area to final capacity of 50,000m3/day. The current phase 2 expansion will increase the plant capacity from 20 ML/d to 30 ML/d.
Completion Date: Spring 2011
 
GWS - Woodbine and Ravenshoe W/M (Church St - Keswick Tank)
Project No. 72180
Contract No. T-08-70, 08-104
Project Description: Watermain - Church Street to Keswick Tank
Completion Date: Winter 2011
 
Kennedy Watermain
Project No. 74260
Project Description:  A joint project with the City of Toronto.
This project is composed of 2 Contracts:
74260.01 - Watermain along Kennedy Road Bypass from the Railway Site to Major Mackenzie Drive ( Open Cut)
74260.02 - Watermain along Kennedy Road Bypass from the Milliken Reservoir site to Railway (Tunnel)
 
Keswick WPCP Expansion
Project No. 72240
Contract No. T-08-72
Project Description:  Phase I expansion will increase the plant treatment capacity by approximately 50 percent from the current 12,070 m3/day up to an average day flow of 18,000m3/day, which is equivalent to a serviced population of approximate 49,300. The phase I expansion project has started in November 2009 and will be completed by the year 2012.
Completion Date:  Autumn 2012
 
King City Elevated Tank and watermain from Elevated Tanks to Town
Project No. 73210
Contract No. T-09-28
Project Description: This work will include the construction of a new elevated tank for King City.
Completion Date: Winter 2011
 
North Richmond Hill Elevated Tank No. 2 and Yonge Vandorf Bloomington Bayview Watermain
Project No. 76300
Contract No. T-09-17
Project Description:  This work involves the planning, design and construction of a new elevated water storage tank in Oak Ridges on the site of the existing elevated tank and the decommissioning of the existing elevated tank. New 900/500mm dia. watermains will be installed on Bloomington, Bayview, Yonge and Vandorf.
Completion Date:  Summer 2014
 
YDSS Duffin Creek WPCP Expansion
Project No. 73720
Contract No.
Project Description:  The Duffin Creek Water Pollution Control Plant (WPCP) processes industrial and municipal wastewater generated from York and Durham Regions. It is the terminus of the York-Durham Sewage System (YDSS) and is located in the City of Pickering on the North shore of Lake Ontario. In order to accommodate growth in York and Durham Region to the year 2035, the plant will need to increase its wastewater treatment capacity from 420 MLD to 630 MLD (50% increase). This will involve two major capital projects.
Completion Date: 2012
 
 

Temporary Road Closures

Related Links

Ontario Ministry of Transportation

City of Toronto Road Restrictions

Contact Us
For further information related to Water & Wastewater, click here to e-mail us.

 
Back to top
 
space