Water and Wastewater Construction Projects

York Region has scheduled projects for building water and wastewater structures and facilities over the next 10 years. This 10 Year Capital Construction Program has been designed to meet the needs of York Region’s rapidly growing population.

View the following maps for an outline of planned water and wastewater projects:


Current Construction Projects:

16th Avenue Sewer System Rehabilitation

York Region is conducting a full sewer rehabilitation of the existing sanitary sewer on 16th Avenue between Mingay Avenue and 9th Line, in the City of Markham.

Completion Date: August, 2019


Aurora Ruben Street Well Modifications

York Region will be working in the Ruben Street community rehabilitating the well at 39 Reuben Street in the Town of Aurora. The work includes sealing the well below the surface, putting in a well cap and installing discharge pipe. When the work is completed, the area around the work site will be restored.

Construction Dates: September 27 to October 31, 2018

Bullock Drive Watermain Construction in the City of Markham

The watermain construction work includes replacing 2km of the existing watermain and value chambers on Bullock Drive between McCowan Road and Laidlaw Blvd.

Completion Date: December, 2018


Holland Landing Prairie Habitat Restoration Project

The restoration project is enhancing biodiversity by reinstating rare native prairie plants which become home to butterflies and species at risk birds such as the Eastern Meadowlark swallows and Bobolink songbird.

The project also includes planting several Butternut trees which have been transplanted from nearby construction areas to the Holland Landing Lagoons.  Butternut trees are a species at risk in Ontario.

Please email any questions or comments to QHLS@york.ca

Completion Date: 2020


Islington Watermain Rehabillitation City of Vaughan

The rehabilitation work is extending the life of the watermain which runs along Islington Avenue from Steeles Avenue West to Highway 7 and west to Kipling Avenue, in the City of Vaughan.

Completion Date: Fall, 2019


Keswick Sewage Pumping Station and Forcemain Upgrades

Improvments are coming to upgrade the Keswick Sewage Pumping Station including upgrades to the forcemain.  The upgrades to the station will not impact service to residents and the station will remain operational during the work.

Construction Date: Fall 2019


Maple Pumping Station Upgrades

York Region is upgrading the Maple Pumping station to ensure the continued supply of safe, quality drinking water to the community.


Newmarket Southeast (Magna) Elevated Tank Upgrades

Construction includes repainting and upgrading the facilities located at  1030 Ivsbridge Blvd. to ensure continued delivery of quality drinking water and extend the lifespan of the tank. 

Completion Date: November, 2018


Schomberg Water Treatment Plant Maintenance

The Schomberg Water Treatment Plant located at 210 Western Avenue in the Township of King will be undergoing maintenance construction activities on the Plant’s water filtration system. This work is being completed to ensure continued delivery of quality drinking water and to upgrade Plant technology. During construction, there will be no service disruption to tap water and it will continue to be clean and safe to drink.

Completion Date: Summer, 2018

View the project updates below for more information:


Stouffville Elevated Tank Repainting and Upgrades

The elevated water tank will be repainted and the facilities upgraded to extend the lifespan of the tank and ensure the continued supply of safe, quality drinking water.

Completion Date: November, 2018


Sutton Water Resource Recovery Facility Expansion

Upgrades and a new tank, please expect additional truck traffic on Black River Road and some noise.

Construction Dates: December, 2018


Toronto Water Metre Upgrades City of Markham and the City of Vaughan

York Region and the City of Toronto are partnering to upgrade 13 Toronto water metre sites located throughout York Region. Phase one of the construction upgrades begin with six sites located in the City of Markham and City of Vaughan.

The roads will remain open to traffic however lane restrictions may be in place.

Completion Date: Summer, 2018


West Vaughan Sewage Servicing

The 14 kilometer sewer starts at the Kleinburg Water Resource Recovery Facility and ending at the Humber Sewage Pumping Station. This new trunk sanitary sewer and pump station upgrades will facilitate growth in the West Vaughan area to 2051.

Construction Begins: 2021


YDSS Duffin Creek Water Pollution Control Plant

Learn about the Duffin Creek Plant here or please visit Durham Region's website for construction information.





Related Resources


Water and wastewater construction,water construction,wastewater construction,construction,sewer construction,sewage system construction,water,sewage system,sewer,sewage,capital construction,10 year capital construction program,capital construction program,construction program,10 year construction program,10 year program The Regional Municipality of York en-US Water and Wastewater Construction Water and Wastewater Construction Projects Learn more about on-going water and wastewater construction projects happening in your community and 10 year construction plans.

News and Social Media

Actions
Loading...

Campaigns and Projects

Actions
Loading...

Contact Us

  • Environmental Services

  • 1-877-464-9675

  • Administrative Centre

  • Accessibility

    Accessible formats or communication supports are available upon request

Water and wastewater construction,water construction,wastewater construction,construction,sewer construction,sewage system construction,water,sewage system,sewer,sewage,capital construction,10 year capital construction program,capital construction program,construction program,10 year construction program,10 year program
url of logo image en-US The Regional Municipality of York Contact Us

Events Calendar


  • More events