Leslie Street and St. John's Sideroad Road Improvements

Transforming Leslie Street and St. John’s Sideroad

Photo of Phase 1, Leslie Street from Broughton Lane to Mulock Drive.

To accommodate growth, York Region is widening and improving Leslie Street, from Wellington Street to Mulock Drive, and St. John’s Sideroad, from Bayview Avenue to Woodbine Avenue, in the Town of Aurora, the Town of Newmarket and the Town of Whitchurch-Stouffville.

We recognize construction can be disruptive and are making every e­ ort to minimize disruption to those living, working and travelling in those areas, and keep all informed with regular updates.

Construction is occurring in three phases:

Phase 1: Leslie Street from Broughton Lane to Mulock Drive

Construction along this section of Leslie Street began in fall 2015 and is now complete. Leslie Street is now open to four lanes.

The work completed includes:

  • Road widened to four lanes
  • New street lighting, on-street bike lanes and sidewalks
  • Intersection improvements and new traffic signals
  • New storm sewer system
  • Watermain extended from Kingdale Road to north of Mulock Drive

Leslie Street and St. John's Sideroad Constrcution Area Graphic Map showing anticipated 2017 road closure. For a detailed description of this map please call 1 877 464 9675 extension 75923.

Phase 2: St. John’s Sideroad from Bayview Avenue to Woodbine Avenue

Construction along this section of St. John’s Sideroad began in summer 2016 and is ongoing.

Road improvements along St. John’s Sideroad between Bayview Avenue and Thomas Phillips Drive/William Graham Drive are approaching completion.

Work in this section includes:

  • Widening the road from two to four lanes
  • Completing bridge construction east of Mavrinac Boulevard
  • Installing street lighting, on-street bike lanes, sidewalks and a multi-use path
  • Replacing existing traffic signals and installing new traffic signals at various intersections
  • Installing a storm sewer system

Major construction for this section of St. John’s Sideroad is scheduled to be completed by end of summer 2017.

St. John’s Sideroad is closed from Thomas Phillips Drive/William Graham Drive to Leslie Street and from Leslie Street to Woodbine Avenue to complete significant work around the Leslie Street intersection.

Work in this section includes:

  • Replacing the culvert west of Leslie Street with a bridge
  • Reducing the slope of the road on both sides of Leslie Street to match York Region road standards
  • Installing a watermain on behalf of the Town of Aurora
  • Installing a sanitary sewer system
  • Resurfacing existing road between Highway 404 and Woodbine Avenue

Major construction is scheduled to be completed by the end of 2017.

Photo, phase 2, st. john's sideroad widening between bayview avenue and thomas phillips drive.

Photo, phase 2, looking west along the closed section of st. john's sideroad.

Phase 3: Leslie Street from Don Hillock Drive to south of Broughton Lane

Construction along this section of Leslie Street began in July 2017.

Work in this section includes:

Widening the road from two to four lanes

  • Replacing two culverts and extending one culvert
  • Installing two pedestrian underpasses
  • Replacing existing traffic signals and installing new tra­ffic signals at various intersections
  • Installing a storm sewer system
  • Installing street lighting, sidewalks and a multi-use path from Don Hillock Drive to State Farm Way

Construction is expected to be completed in 2018.

Safety

Safety is a top priority on all Regional construction sites. Please contact us if you observe any unsafe issues in and around this site.

Motorists are advised to follow all construction traffic signals and reduce their speed through the construction area.

Transit Services

For inquiries about transit routes during construction, riders are encouraged to visit yrt.ca or call 1-866-MOVE-YRT (668-3978).

We are here to answer your questions. Accessible formats or communication supports are also available upon request. Please contact us for more information.

General Inquiries:
Christine Morrison
Communications and Community Engagement Specialist, York Region
Office: 1-877-464-9675, ext. 75923
Email: christine.morrison@york.ca

Phase 1 Construction Activity:
Abdus Sobahan
Construction Administrator, York Region
Office: 1-877-464-9675, ext. 75930
Email: abdus.sobahan@york.ca


Send me Leslie Street and St. John's Sideroad enews! Please add me to the distribution list.

 



View Leslie Street and St. John's Sideroad road improvements photo gallery


 

Leslie Street,St. John's Sideroad,construction,roads,improvements,Town of Aurora,Town of Newmarket,building,communities,project,maintenance The Regional Municipality of York is improving Leslie Street and St. John's Sideroad for motorists, pedestrians and cyclists. The Regional Municipality of York en-US News