King Road and Weston Road Intersection Improvements
January 6, 2021
Transforming the intersection of King Road and Weston Road

The Regional Municipality of York is investing in building a safe, efficient and reliable Regional transportation network for all users. We are improving the intersection of King Road and Weston Road in the Township of King to accommodate growth and improve traffic flow.
Construction Update
Since construction began in mid-July 2019, the following improvements have been completed:
- Road widening work on the south side and north side of King Road
- Installation of upgraded permanent tra c signals at King Road and Weston Road
- Installation of retaining walls along King Road
- Construction of the slopes on the side of the road
- Construction of the ditches on the side of the road to help funnel water from the road
Construction will not be completed until early summer 2021 due to a delay in unforeseen site and weather conditions. The remaining work to be completed includes:
- Final top layer of asphalt paving and line markings on King Road and Weston Road
- Final clean up and restoration of the area
Construction has shut down for the winter and will resume in spring 2021.
For more information on this project and other projects visit the Road Construction Schedule page.
Reminders
This work may be rescheduled due to weather conditions or delays related to COVID-19 Public Health guidelines. York Region will provide advance notice whenever possible.
We are here to answer your questions. Accessible formats of this news item or communication supports are also available upon request.
General Inquiries:
Capital Planning and Delivery
Office: 1-877-464-9675
Email: transportation@york.ca
Construction Activity:
Matthew Jebb
Construction Administrator
Office: 1-877-464-9675 ext. 75233
Email: transportation@york.ca
After hours emergency: 1-877-464-9675 ext. 75200