Road Construction Schedule

Notice:

York Region’s number one priority remains protecting the health and safety of staff and all our communities. As we monitor the ongoing COVID-19 situation in York Region, we continue to deliver essential services while staying current with all health and safety-related information and complying with guidelines related to COVID-19 published by the Ontario Ministry of Health, Ministry of Labour, Training and Skills Development and York Region Public Health.

York Region is dedicated to matching transportation system growth with the growth of our communities. Below are York Region's road construction and improvement projects.

For information on vivaNext construction projects, visit vivaNext.


Current and Upcoming Construction

Last updated: June 2, 2020

Accessible formats or communication supports are available upon request by contacting the Transportation Services department at 1-877-464-9675 ext. 75000.



Please note that these projects are only road realated projects for water and waste water projects please visit the Water and Wastewater Construction page.


For comments on the map, please complete the feedback form.


Please select a municipality to view current road construction projects and ongoing Environmental Assessment Studies.

Construction maps are also available under Related Resources at the bottom of the page.

Aurora

Bayview Avenue — Lake to Lake Cycling Route and Walking Trail
Construction Starts: September 2019
Construction Ends: Spring 2020

Leslie Street from Wellington Street to Broughton Lane
Road widening from 2 to 4 lanes
Construction Starts: Spring 2017
Construction Ends: Spring 2020

St. John's Sideroad from Bayview Avenue to Leslie Street
Road widening from 2 to 4 lanes
Construction Starts: July 2016
Construction Ends: Spring 2020

Yonge Street from Henderson Drive to Industrial Parkway South
Road rehabilitation
Construction Starts: May 2020
Construction Ends: Late 2020

AURORA The Regional Municipality of York en-US

East Gwillimbury

Kennedy Road and Ravenshoe Road
Flashing beacon installation
Notice of Road Construction
Construction Starts/Ends: May 2020

Woodbine Avenue
Mount Albert Road to Highway 404
Notice of Road Resurfacing
Construction Starts: May 4, 2020
Construction Ends: Fall 2020

Yonge Street from Davis Drive to Green Lane
Road widening from 4 to 6 lanes
Construction Starts: 2022

EAST GWILLIMBURY The Regional Municipality of York en-US

Georgina

Kennedy Road and Ravenshoe Road
Flashing beacon installation
Notice of Road Construction
Construction Starts/Ends: May 2020
Georgina The Regional Municipality of York en-US

King

Davis Drive and Jane Street
New traffic signal installation
Notice of Road Construction
Construction Starts: Fall 2019
Construction Ends: Spring 2020

Jane Street East Humber River Bridge Rehabilitation
200 metres north of King Road
Notice of Road Construction
Construction Starts: Spring 2020
Construction Ends: Fall 2020

Jane Street from King Road to King Vaughan Road
Culvert work
Notice of Temporary Road Closure
Construction Starts: May 11, 2020
Construction Ends: May 16, 2020

King Road
8th Concession to Weston Road and West of Highway 27
Notice of Road Resurfacing
Construction Starts: Spring 2020
Construction Ends: Fall 2020

King Road King Horn Bridge Rehabilitation
800 metres east of Highway 400
Notice of Road Construction
Construction Starts: Spring 2020
Construction Ends: 2021

King Road at Weston Road
Intersection improvements
Construction Starts: Summer 2019
Construction Ends: Fall 2020

King The Regional Municipality of York en-US

Markham

16th Avenue from Woodbine Avenue to York/Durham Line
This study investigates future long term needs and improvements for 16th Avenue to better serve transit, pedestrians, cyclists, and motorists.  The study considers prior studies and official plans and effects on the environment.
Estimated Study Completion: 2020

16th Avenue from Yonge Street to Woodbine Avenue
This study investigates future long term needs and improvements for 16th Avenue to better serve transit, pedestrians, cyclists, and motorists.  The study considers prior studies and official plans and effects on the environment.
Study Completed: 2018

19th Avenue and Kennedy Road
New traffic signal installation
Notice of Construction
Construction Starts: May 2020
Construction Ends: August 2020

19th Avenue and Warden Avenue
New traffic signal installation
Notice of Construction
Construction Starts: May 2020
Construction Ends: August 2020

19th Avenue and Woodbine Avenue
New traffic signal installation
Notice of Construction
Construction Starts: May 2020
Construction Ends: August 2020

Bayview Avenue from 16th Avenue to Steeles Avenue
Road resurfacing
Notice of Construction
Construction Starts: May 4, 2020
Construction Ends: Fall 2020

Cedar / Red Cedar Avenue
Environmental Assessment Study
Estimated Study Completion: Spring 2020

Highway 7 and Albert Street/Cosburn Road
Traffic Signal Improvements
Notice of Road Construction
Construction Starts: November 2019
Construction Ends: Spring 2020

Highway 7 from Allstate Parkway to Town Centre Boulevard
Road Resurfacing
Notice of Road Construction
Construction Starts: May 11, 2020
Construction Ends: Fall 2020

Highway 7 and Wootten Way North/South
Traffic Signal Upgrades
Notice of Traffic Signal Modifications
Construction Start: April 2020
Construction Ends: Summer 2020

Highway 404 Road Crossing North of 16th Avenue
Construction of a new bridge over Highway 404 to link Orlando Avenue with Markland Street
Construction Starts: 2022

Kennedy Road from Steeles Avenue to Major Mackenzie Drive
Environmental Assessment Study
Construction Starts: 2023 to beyond 2029

Leslie Street and Commerce Valley Drive West/East
Intersection Improvements
Notice of Road Construction

Construction Starts: April 2020
Construction Ends: September 2020

Leslie Street and Green Lane/Summerdale Drive
Intersection Improvements
Notice of Road Construction
Construction Starts: April 2020
Construction Ends: September 2020

Leslie Street and John Street
Intersection Improvements
Notice of Road Construction
Construction Starts: April 2020
Construction Ends: September 2020

Markham Road and Denison Street
Traffic Signal Upgrades
Notice of Construction
Construction Starts: April 2020
Construction Ends: Summer 2020

McCowan Road from Steeles Avenue to Major Mackenzie Drive
Environmental Assessment Study
Construction Starts: 2026 to beyond 2029

Ninth Line from Fincham Avenue to Tiers Gate/White's Hill Avenue
Road Improvements
Notice of Road Construction Update
Construction Starts: April 23, 2020
Construction Ends: Fall 2020

Markham The Regional Municipality of York en-US

Newmarket

Davis Drive from Yonge Street to Highway 404
Road resurfacing
Notice of Road Improvements
Construction Starts: May 19, 2020
Construction Ends: fall 2020

Mulock Drive from Yonge Street to Highway 404
Road resurfacing
Notice of Road Improvements
Construction Starts: May 19, 2020
Construction Ends: fall 2020

St. John's Sideroad from Bayview Avenue to Leslie Street
Road widening from 2 to 4 lanes
Construction Starts: July 2016
Construction Ends: Spring 2020

Yonge Street from Davis Drive to Green Lane
Road widening from 4 to 6 lanes
Construction Starts: 2022

Yonge Street — Mulock Drive to Davis Drive
vivaNext bus rapidway construction

Newmarket The Regional Municipality of York en-US

Richmond Hill

16th Avenue and Berwick Crescent
Traffic Signal Upgrades
Notice of Road Construction Update
Construction Start: December 2019
Construction Ends: Spring 2020

16th Avenue from Woodbine Avenue to York/Durham Line
This study investigates future long term needs and improvements for 16th Avenue to better serve transit, pedestrians, cyclists, and motorists.  The study considers prior studies and official plans and effects on the environment.
Estimated Study Completion: 2020

16th Avenue from Yonge Street to Woodbine Avenue
This study investigates future long term needs and improvements for 16th Avenue to better serve transit, pedestrians, cyclists, and motorists.  The study considers prior studies and official plans and effects on the environment.
Study Complete: 2018

19th Avenue from Bayview Avenue to Leslie Street
Road widening from 2 to 4 lanes
Construction Starts: 2021

Bathurst Street from Major Mackenzie Drive to Elgin Mills Road
Road widening from 4 to 6 lanes, including Transit-HOV lanes
Construction Starts: Beyond 2029

Bathurst Street from North of Highway 7 to Rutherford Road
Road widening from 4 to 6 lanes, including Transit-HOV lanes
Construction Starts: 2023

Bathurst Street from Rutherford Road to Major Mackenzie Drive
Road widening from 4 to 6 lane, including Transit-HOV lanes
Construction Starts: 2024

Bayview Avenue from 16th Avenue to Steeles Avenue
Road resurfacing
Notice of Construction
Construction Starts: May 4, 2020
Construction Ends: Fall 2020

Bayview Avenue North of Highway 7 to 16th Avenue
Road improvments including widening from 4 to 6 lanes
Construction Starts: 2025

Carrville Road from Bathurst Street to Yonge Street
Road resurfacing
Notice of Road Construction
Construction Starts: Early September 2019
Construction Ends: Spring 2020

Cedar / Red Cedar Avenue
Environmental Assessment Study
Estimated Study Completion: Spring 2020

Elgin Mills Road between Bathurst Street and Yonge Street
Road widening from 3 to 4 lanes
Construction Starts: 2026

Highway 404 Midblock Crossing North of 16th Avenue
Construction of a new bridge over Highway 404 to link Orlando Avenue with Markland Street
Construction Starts: 2022

King Road from Yonge Street to Bond Crescent
Reconstruction of exisitng 4 lane road
Construction Starts: 2022

Leslie Street from 19th Avenue to Stouffville Road
Environmental Assessment Study
Construction Starts: To be determined

Leslie Street from Elgin Mills Road to 19th Avenue
Road widening from 2 to 4 lanes
Newsletter
Construction Starts: Fall 2019
Construction Ends: Summer 2021

Leslie Street and West/East Beaver Creek Road
Intersection Improvements
Notice of Road Construction
Construction Starts: April 2020
Construction Ends: September 2020

Leslie Street and West/East Wilmot Street
Intersection Improvements
Notice of Road Construction
Construction Starts: April 2020
Construction Ends: September 2020

Major Mackenzie Drive from Bayview Avenue to Leslie Street
Road repaving
Notice of Road Construction
Construction Starts: Mid-September 2019
Construction Ends: Spring 2020

Yonge Street –  Highway 7 to 19th Avenue/Gamble Road
vivaNext bus rapidway construction

Richmond Hill The Regional Municipality of York en-US

Vaughan

Bathurst Street and Centre Street from Highway 7 to Yonge Street
vivaNext bus rapidway construction

Bathurst Street from Major Mackenzie Drive to Elgin Mills Road
Road widening from 4 to 6 lanes, including Transit-HOV lanes
Construction Starts: Beyond 2029

Bathurst Street from North of Highway 7 to Rutherford Road
Road widening from 4 to 6 lanes, including Transit-HOV lanes
Construction Starts: 2023

Bathurst Street from Rutherford Road to Major Mackenzie Drive
Road widening from 4 to 6 lane, including Transit-HOV lanes
Construction Starts: 2024

Highway 7 from Highway 27 to Islington Avenue
Road resurfacing
Construction Starts: Summer 2020
Construction Ends: Fall 2020

Highway 27 CP Rail Bridge Replacement
Bridge replacement 300 metres south of Rutherford Road
Construction Starts: December 2019
Construction Ends: Spring 2022

Highway 50 from Major Mackenzie Drive to Albion-Vaughan Road
Road widening from 4 to 6 lanes
Construction Starts: 2026

Highway 50 from Rutherford Road to Major Mackenzie Drive
Road widening from 4 to 6 lanes
Construction Starts: 2024

Highway 50 at Mayfield Road
Intersection Improvements 
Construction Starts: 2026

Highway 7 from Bruce Street to Edgeley Boulevard
vivaNext bus rapidway construction

Highway 427 Road Crossing North of Langstaff Road
Construction Starts: 2023

Islington Avenue from Steeles Avenue to Highway 7
Road resurfacing
Construction Starts: Summer 2020
Construction Ends: Fall 2020

Jane Street from King Road to King Vaughan Road
Culvert work
Notice of Temporary Road Closure
Construction Starts: May 11, 2020
Construction Ends: May 16, 2020

Keele Street and Dina Road
Traffic Signal Upgrades
Notice of Road Construction
Construction Start: Spring 2020
Construction Ends: Summer 2020

Keele Street, north of Teston Road
Bridge work
Notice of  Construction
Construction Starts: October 2019
Construction Ends: Summer 2020

Keele Street from Steeles Avenue to Highway 407
Road widening from 4 to 6 lanes, including Transit-HOV lanes
Construction Starts: Fall 2020
Consttruction Ends: 2023

Langstaff Road from Weston Road to Highway 7
Environmental Assessment Study
Estimated Study Completion: Fall 2020

Major Mackenzie Drive City Hall
Intersection Improvements
Construction Starts: August 2020
Construction Ends: Fall 2020

Major Mackenzie Drive
Dufferin Street to Bathurst Street
Notice of Road Resurfacing
Construction Starts: Spring 2020
Construction Ends: Summer 2020

Major Mackenzie Drive from Islington Avenue to Pine Valley Drive
Road widening from 2 to 6 lanes
Notice of Road Construction
Construction Starts: Summer 2019
Construction Ends: Fall 2021

Major Mackenzie Drive from the Highway 427 Extension to Islington Avenue
Road widening from 2 to 6 lanes, including jog elimination
Construction Update — Canadian Pacific Railway Bridge Construction
Construction Starts: Spring 2018
Construction Ends: 2021

Major Mackenzie Drive from Highway 400 to Jane Street
Road widening from 4 to 6 lanes
Construction Starts: Late summer/fall 2020
Construction Ends: Late 2022

Major Mackenzie Drive from Highway 50 to the Highway 427 Extension
Road widening from 2 to 6 lanes
Notice of Road Construction
Construction Starts: May 2020
Construction Ends: Late 2020

Major Mackenzie Drive West at McNaughton Road/Avro Road
Culvert replacement and road closure
Construction Starts: June 2019
Construction Ends: Complete

Highway 27 from Highway 407 to Langstaff Road
Resurfacing
Notice of Road Construction
Construction Starts: July 2019
Construction Ends: Spring 2020

Rutherford Road from Jane Street to Westburne Drive
Road widening from 4 to 6 lanes
Constructions Starts: August 2020
Construction Ends: Spring 2023

Rutherford Road from Peter Rupert Avenue to Bathurst Street
Road widening from 4 to 6 lanes, including Transit-HOV lanes
Construction Starts: 2022

Rutherford Road from Westburne Drive to Peter Rupert Avenue (underpass)
Metrolinx project: Road underpass and widening from 4 to 6 lanes, including Transit-HOV lanes
Construction Starts: 2019

Teston Road IEA from Keele Street to Bathurst Street
Individual Environmental Assessment Study
Construction Starts: Beyond 2029

Teston Road from Pine Valley Drive to Weston Road
Roading widening from 2 to 4 lanes, including jog elimination
Construction Starts: 2021

Vaughan The Regional Municipality of York en-US

Whitchurch-Stouffville

Bloomington Road from Highway 48 to Ninth Line
Resurfacing
Notice of Road Construction
Construction Starts: September 9, 2019
Construction Ends: Spring 2020

St. John's Sideroad from Bayview Avenue to Leslie Street
Road widening from 2 to 4 lanes
Construction Starts: July 2016
Construction Ends: Spring 2020

Whitchurch-Stouffville The Regional Municipality of York en-US


Related Resources

 


Roads,road work,construction,bridge repairs,road widening,current projects,upcoming projects The Regional Municipality of York en-US Road Construction Schedule Road Construction Schedule Current and upcoming Regional road improvement and construction projects help York region meet the needs of growing communities.